Catesby Estates plc, working in partnership with the Europa Way Consortium have been preparing the site at Myton Green, Warwick in readiness for the start of strategic infrastructure works to support the new residential development of 735 new homes.

The land has been cleared, and the initial ecology works and demolition of some of the dilapidated farm buildings has been completed.

Infrastructure works starts spring 2018 and will last around 56 weeks including the delivery of the first section of a tree-lined community spine road, which will eventually link Europa Way with Gallows Hill, along with the creation of an extensive green corridor adjacent to Myton Brook.

Matthew Brighton, Senior Commercial Manager at Catesby Estates, said: “The new homes will offer a range of sizes and styles with the first residents taking occupation during 2019.  In time, the development will deliver six equipped play areas, a network of new footpaths and cycleways along with the planting of more than 250 specimen trees set in around 20 acres of green open space.”